Recent Photo Of Canada's New National Soccer Stadium Nearing Completion.
Current Progress (as of Jan. 30/07)
During the month of January, the majority of the building envelope was completed. Media level glazing was completed with the exception of operable vents. The majority of soffit work surrounding the gondola roof on the west side of the stadium was completed. Suite glazing and doors were installed. Finishes to ground floor curtain wall are nearing completion.Insulation and drywall work inSuites 1-26 was completed and drywall taping progressed well within these suites. Completion of taping to these suites is scheduled for February 2, 2007.
Approximately 90% of all tile work has been completed to date. This includes floor tile to dressing rooms and all tile work within wet areas (showers).
Mechanical and electrical fixtures and finishes continued throughout the west side of the stadium and select electrical panels were energized to provide permanent lighting to various locations.The permanent Group Sales structures at the north end of the stadium progressed well and will be fully enclosed during the month of February.
Cash Allowance contracts such as Communications Cabling (The Plan Group), Stadium Audio System (Westbury National), Concession F&B Fit-Up (Electrical – The Plan Group, Mechanical – Modern Niagara) and electrical work associated with Advertising Signage (The Plan Group) all progressed significantly and will continue throughout the month of February. During the month of February, the prime focus will be interior finishes. Completion of interior finishes will allow verification of fire alarm to commence. Verification of the fire alarm system is scheduled for completion by March 16, 2007. The remaining building envelope will also be completed throughout the facility. The remaining hard landscaping will recommence towards the end of the month and is scheduled for completion prior to March 31, 2007.
Current Progress (as of Jan. 30/07)
During the month of January, the majority of the building envelope was completed. Media level glazing was completed with the exception of operable vents. The majority of soffit work surrounding the gondola roof on the west side of the stadium was completed. Suite glazing and doors were installed. Finishes to ground floor curtain wall are nearing completion.Insulation and drywall work inSuites 1-26 was completed and drywall taping progressed well within these suites. Completion of taping to these suites is scheduled for February 2, 2007.
Approximately 90% of all tile work has been completed to date. This includes floor tile to dressing rooms and all tile work within wet areas (showers).
Mechanical and electrical fixtures and finishes continued throughout the west side of the stadium and select electrical panels were energized to provide permanent lighting to various locations.The permanent Group Sales structures at the north end of the stadium progressed well and will be fully enclosed during the month of February.
Cash Allowance contracts such as Communications Cabling (The Plan Group), Stadium Audio System (Westbury National), Concession F&B Fit-Up (Electrical – The Plan Group, Mechanical – Modern Niagara) and electrical work associated with Advertising Signage (The Plan Group) all progressed significantly and will continue throughout the month of February. During the month of February, the prime focus will be interior finishes. Completion of interior finishes will allow verification of fire alarm to commence. Verification of the fire alarm system is scheduled for completion by March 16, 2007. The remaining building envelope will also be completed throughout the facility. The remaining hard landscaping will recommence towards the end of the month and is scheduled for completion prior to March 31, 2007.